Below is a list of jobs that need to be completed before the end of Summer 2010. Please check off items as you complete them!
- Fix broken stuff - If it has a trouble card on it, fix it!
- 321 Transformers - Convert all the 6.3V transformers to accept standard AC power plugs.
- 200 Level Optics - New glass lenses must be put into the 200 level geometric optics carts.
- Eye Model De-Liming - Oh god, not this again.
- Light blocks for Optics - New black cloths must be sized and cut (30"x30" squares)
Photo Review 2010 - Every lab room will be restored to photo review condition. Make changes to the photo review where needed.
- Junk room clearout and conversion to 103.
- Switch 4136/3136
This is a list of things that Brett has been meaning to do forever, but hasn't gotten around to:
- Resizing e/m tube mounts
- Complete conversion of 200 level optics carts.
- New PMT for single photon lab
- Fix optical pyrometer in 307